Planning refractory work for a shutdown: a practical checklist

JISPL teamOctober 20265 min read

Refractory work is often on the critical path of a shutdown. When it overruns, the whole plant waits. Most delays can be avoided with planning done weeks before the stop.

6 to 8 weeks before

  • Review inspection records, shell scans and previous repair history
  • Define the scope: zones, areas and lining thickness to replace
  • Fix the lining design, materials and quantities
  • Place material orders, especially for special shapes and castables

2 to 4 weeks before

  • Confirm material dispatch dates and test certificates
  • Agree the day-by-day schedule, crew size and shifts with the contractor
  • Plan cooling time, access, scaffolding and lighting
  • Complete permits, HSE induction and method statements

During the shutdown

  • Hold a short daily progress meeting
  • Inspect the shell and anchors once the old lining is removed
  • Check joints, expansion allowances and anchoring as work proceeds
  • Keep spare material for surprises found during demolition

Before startup

  • Complete a joint inspection of the finished lining
  • Agree and follow the heat-up and dry-out schedule
  • Collect documents: drawings, test certificates, dry-out chart and completion report

With an annual maintenance contract, JISPL handles inspection, scoping and material planning in advance, so your shutdown slot is ready before the plant stops.

Need help with this on your plant?

Send us the details and get a quick quotation or a site visit.

Talk to us

Need material, a lining job, or both?

Send the grade and quantity for rates, or a drawing, BOQ or photo for a job quotation. We reply with a quick quotation.

Quick quote

Tell us what you need

Enter your name.
Enter a valid phone number.

We reply quickly. Your details are used only to answer your enquiry.

WhatsApp